EEE8087
Real Time Embedded Systems
Worksheet 4. The Time-Slicing Structure
This week we startwork on the central components of an elementary real-time operating system (RTOS) that divides the processor's time between separate user tasks. These tasks will need to communicate with the system, and will request its services by means of a 'software interrupt'.
Implementation of Software Interrupts
A software interrupt is known as a 'trap'. It causes the processor to respond in a very similar way as it does to a hardware interrupt, and so allows system calls from the user program and interrupts from hardware devices to enter the operating system in a consistent way.
There are 16 trap instructions available, numbered 0 to 15, and written
trap #0
...
trap #15
Each of the 16 trap instructions may have its own interrupt service routine (ISR). After pushing the PC and SR, the processor then accesses a table in low memory, at address 80H. As for the hardware interrupts, the table contains a 4-byte value corresponding to the address of the ISR for each software interrupt. Vectors for the two types of interrupt will normally be combined into a single block of code.
|
|
;interrupt vectors |
|
org |
$64 ;origin 64H |
hvec1 |
dc.l |
hisr1 ;address of hardware ISR 1 |
hvec2 |
dc.l |
hisr2 ; ... etc |
|
org |
$80 ;origin 80H |
svec0 |
dc.l |
sisr0 ;address of software ISR 0 |
svec1 |
dc.l |
sisr1 ; ... etc |
Controlling Interrupts
There is, however, an important difference between hardware and software interrupts. Hardware interrupts are in order of priority, with 7 being the highest priority and 1 the lowest. If two hardware interrupts occur at the sametime, then the one at the higher priority will be accepted and the other one will be kept waiting until the first ISR has completed. If a hardware interrupt occurs shortly after another one, but while the ISR for the first interrupt is still in execution, then the processor will again compare the priorities of the two interrupts. If the new interrupt is of a higher priority, then it will interrupt the lower priority ISR. If the new interrupt is at a lower priority than the currently executing ISR, it will be kept waiting until that ISR completes.
Software interrupts do not behave in an analogous way. Since the processor can only execute one instruction at a time, it would be impossible for two software interrupts to occur at the sametime, and unless a programmer includes atrap instruction within an ISR, there will also be no occasions on which a trap takes place during the processing of another trap. There is therefore no point in prioritising the software interrupts, and all 16 are at the same priority. There is, however, the question of the relative priority of the hardware and software interrupts. What if a hardware interrupt is raised at the sametime as the processor is executing a software interrupt instruction? This is handled by assigning all the software interrupts to priority level 0. Processing of a software interrupt is therefore interruptible by a hardware interrupt at any of the priority levels 1 to 7.
Within your system, however, regardless of the type of interrupt being processed, you will want to prevent the acceptance of any other interrupt. Your system will therefore be completely uninterruptible. Once entered, it will always run to completion and then return to the user task that was running when the interrupt was raised. You will therefore need to disable interrupt acceptance, the procedure for which is explained now.
Using the simulator, examine the 16-bit status register. Bits 8, 9 and 10 (labelled 'INT') hold a 3-bit value that represents the interrupt priority mask. When an interrupt is accepted, the mask is set to the priority level of that interrupt. A hardware interrupt will only be accepted if its priority is greater than the current setting in the mask. Normally, the mask is set to 000 (decimal 0) thereby allowing the acceptance of any hardware interrupt. However, it will remain at zero during its response to a software interrupt, since that is the priority of these interrupts, and will thereby allow the hardware to interrupt the software ISR. If you wish to prevent this, then the following instruction, placed at the very start of a software ISR, sets the mask to binary 111 (decimal 7). Any hardware interrupts will now be disabled, and held pending until the mask is returned to zero.
or #$0700,sr ;disable hardware interrupts
The status register will have been automatically saved on the stack at the start of the interrupt servicing. On execution of the 'return from exception' instruction (RTE), it will be restored, and the mask reset to the zero value that it held previously, thereby allowing the acceptance of any hardware interrupt that might have been raised in the meantime and is currently pending.
If you want to enable hardware interrupts at any other time, the following instruction will set the mask to zero.
and #$f8ff,sr ;enable hardware interrupts*
Practical Work
Assessment question
Work in groups of three on this question. Your submission should include the following.
Your software, including the RTOS and the test programmes you used to demonstrate it. Submit the source code, not the assembler output listing.
Documentation: a .PDF file is preferable, otherwise .DOC.
The names and student numbers of all three group members should be shown on the software heading and on the frontpage of the documentation.
There are therefore two items to be submitted: a single software file, and the documentation. These items should be placed into a single zipped file, and uploaded to a Canvas submission point to be advised. The submission deadline is 2pm on Friday 17th January, 2025.
Each item will now be described in detail.
The RTOS
The work consists of writing a basic time-slicing system, along the lines of the one discussed in the lecture. It should allow the execution of several concurrent user tasks, with support for task scheduling and inter-task communication. An outline programme is provided on Canvas, but you will write the service routines (including reset), the scheduler, and the user tasks for each application.
The user tasks are located in memory, above the system itself. Each task has its own area of memory, with the programme code at the lowest address, data above it, and top-of-stack at the next address above this task's memory area. For example, the following task occupies memory between 2000H and 2FFFH. It has its code at 2000H, data at 2C00H, and stack at the top of the data area.
Address |
|
2000H |
Programme code |
2C00H |
Data |
3000H |
Top-of-stack |
The system runs in the foreground, and is entered following either a timer interrupt, a software interrupt from one of the tasks requesting service, or another hardware interrupt.
The following system calls should be supported by means of software interrupts. They can either each be allocated to a separate trap number, or (as in the demonstration system) they can all be called on the same trap, with one of the registers used to hold a value identifying the requested function. Some of the calls also require additional parameters in other registers.
1. Create task
Function: A currently unused TCB is marked as in use and set up for a new task.
It is placed on the ready list. The requesting task remains on the ready list. Two parameters indicate the start and end of the memory area occupied by the new task and its data.
Parameters: The start address of the new task,
The address of its top-of-stack.
2. Delete task
Function: The requesting task is terminated, its TCB is removed from the list and marked as unused. Any memory allocated to it is returned to the system.
Parameters: None.
3. Wait mutex
Function: If the mutex variable is one, it is set to zero and the requesting task is placed back onto the ready list. If the mutex is zero, the task is placed onto the wait list, and subsequently transferred back to the ready list when another task executes a signal mutex.
Parameters: None.
4. Signal mutex
Function: If the mutex variable is zero, and a task is waiting on the mutex, then that task is transferred to the ready list and the mutex remains at zero. If the mutex is zero and notask is waiting, the mutex is set to one. In either case, the requesting task remains on the ready list.
Parameters: None.
5. Initialise mutex
Function: The mutex is set to the value 0 or 1, as specified in the parameter.
Parameters: 0 or 1.
6. Wait time
Function: The requesting task is placed onto the wait list until the passage of the number of timer interrupts specified in the parameter, when it is transferred back to the ready list.
Parameters: Number of timer intervals to wait.
An additional function is executed automatically at start-up, or if the user presses the reset button.
System reset
Function: The system is initialised: all internal variables are reset, and each TCB is marked as unused. A TCB for task T0 is then created, and T0 becomes the running task.
A practical RTOS would also include the following functions. These are not required in your submissions, but they are mentioned here for completeness of these notes.
7. Wait I/O:
Function: The requesting task is placed onto the wait list, until an interrupt signifies completion of an I/O operation, when the task is transferred back to the ready list.
Parameters: None.
8. Allocate memory
Function: For tasks that require a large amount of memory, it is more efficient to allocate it as required when the task runs. A large area of memory is therefore kept free within the system, and a block from it, of say 16 kbytes, is returned to the requesting task. If the request is satisfied, the requesting task remains on the ready list. If there is insufficient free memory available, then the requesting task is put on the wait list until memory is returned when another task terminates.
Parameters: On return, the start address of the allocated memory is held in the parameter register.
The system assumes that a default user task, T0, is present. The system runs this task immediately after a reset. It will need to be located at a predetermined address, which will be coded into the reset function.
Your system should be robust, and deal with errors in an intelligent way. For example, what if the user tries to create more tasks than there are available TCBs?
Test programmes
Test your system using the following programmes. You will recognise these as modified versions of the questions in last week's worksheet, this time running under your RTOS.
1. Testing create task and wait time functions.
A stopwatch counts in seconds. It starts when button 0 is pressed and stops when the button is pressed again. The display shows two digits, and should be neatly formatted with unused digits blanked. It is programmed as follows.
Timer interrupts are set to 100ms. Task 0 starts task 1, and both tasks run concurrently. A shared variable running is held in a memory location, and is set by T1 and read by T0. T0 displays a 2- digit value on the 7-segment display, initialised to zero. If running is set, T0 increments the
display, then waits for 10 time intervals, and then repeats. If running is not set, T0 does nothing. T1 tests pushbutton 0. Each time the button is pressed, running changes state.
2. Testing initialise mutex, wait mutex, and signal mutex functions.
A radiation monitor contains two devices that each generate a pulse each time a particle of ionising radiation is detected. The system alternately samples each detector for 100 ms, and records the count, a and b, from each device. It also keeps a running total of the two counts, c = a + b. The system measures the time since it started, and after 8 seconds displays the average count per second between the two detectors, that is, (2c / 2) / 8, or c / 8. (Because it monitors each detector for only half the time, there is an implicit assumption that the total for that detector is twice its actual count.) If at anytime during the 8-second measurement interval the total count c exceeds a certain critical value, the system immediately displays a danger warning by lighting the RH LED, and then continues running for the remainder of the 8 seconds. The LH LED is used to indicate an internal error, as will be explained later.
It would be convenient to indicate a detection by pressing a button, but since we need to test this
system in real-time, and it is not possible to press the buttons hundreds of times per second, we will simulate a fast arrival rate of detection pulses simply by programming the system to increment the two counters continuously. The programming is as follows.
Timer interrupts are set to 100ms. Three tasks run concurrently. After performing any initialisation, tasks 0 and 1 update the counters, either a and c, or b and c, using the following instruction sequence which is repeated continuously.
move.l a,d0
add.l #1,d0
move.l d0,a
move.l c,d0
add.l #1,d0
move.l d0,c
At the end of this sequence, variable c is tested to determine whether it has exceeded the critical value, and if so, the RH LED is lit to indicate a danger condition.
You will note that variable c is updated by both tasks, which are liable to interfere with each other. A mutex operation is therefore used to enforce exclusion and prevent simultaneous updates. A call to mutex wait should be placed before the three instructions that increment this variable, and a signal call at their end.
Task 2 waits for 8 seconds, then displays the result c / 8 on the 7-segment display. (The division can be done by shifting; see the notes for week 1.) The result may be shown in hexadecimal, which avoids doing a conversion to decimals. This task also checks that the mutex functions have worked: if the final value of a + b - c > 1, then there has been an error and this is indicated by lighting the LH LED.
Submitting the test programmes.
Your test programmes should be included at the end of your RTOS code. Place both programmes together, calling them prog1 and prog2. At the start of the user code, put the following branch instructions.
org usrcode
bra prog1
; bra prog2
By commenting out one of these instructions, as has been done for prog2 above, it is easy to select the other for running.
This is a much better arrangement than keeping two versions of the RTOS, with a different test programme in each, or pasting each test programme into the RTOS whenever it is required.
However, since both programmes will be assembled together, you will have to ensure that you use different identifier names within the two programmes. You could, for example, start all labels and variable names within prog1 with 'p1' and those in prog2 with 'p2'.
Documentation
This consists of a user manual. It will explain your system to a user, and will therefore focus on what it does and how to use it. It will include a brief overview of how the system works internally, but only to an extent that is required for the programmer to use the system correctly. It should be structured as follows.
1. A general description, including, for example:
explanation of the principles of multitasking and time-slicing, and how they are implemented; description of the memory layout of the user tasks as shown above;
explanation of the startup behaviour: a default task runs, which may then start other tasks.
2. An itemised description of each of the user functions and their parameters. Explain all aspects of the behaviour of each function that are of interest to the user. For example, when a new task is created, does it run immediately, or is it put at the end of the ready queue? What if two tasks are waiting for the sametime, and so become ready together? Your descriptions should also state how long each function takes to execute. This time should be quoted in terms of instructions, and may be within a specified range, e.g., a particular function might execute in 30 - 50 instructions.
3. A short note about your two test programmes. How do they demonstrate that the system is working? Were there any unresolved problems with them?
With normal typeface and spacing (such as used here) it would be reasonable to expect a length of no more than five or six pages. Submission in .PDF format is preferred, but .DOC(X) is also acceptable.