`UNIVERSITY OF TECHNOLOGY SYDNEY
FACULTY OF ENGINEERING
Floodplain Management 49117
Assignment 4B
Assignment covering Evacuation Management

1) Briefly describe the NSW emergency planning framework and the SES planning process. Explain how flood warning systems and flood intelligence databases are used to in evacuation management planning and operations. Describe the role of community education in enhancing preparedness for evacuation of communities during flood.

2) Evacuation Time Modelling based on Nevagazunda. Develop an evacuation strategy for the town of Nevagazunda in the event of a 100 year ARI (1% AEP) flood. Based on this strategy develop an evacuation timeline. Use the data availablein the Nevagazunda (Part 1) exercise to develop the time line. Assume that all bridges will have1 lane operational for evacuation during floods and 600 cars can pass per hour per lane. Stateany assumptions that you make.

Make recommendations to increase the evacuation time available.

The entire assignment must be submitted as a single report in Word or PDF format. Please submit in UTSonline dropbox (under assignment folder

This assignment is worth 25% of the total assessment load for this subject.

Figure: Nevagazunda 100 yr stage hydrograph

Marking Criteria

NSW Emergency Planning Framework
5
SES Planning Process with discussion on each step
10
Evacuation Management Planning & Operation including Warning
10
System and Flood intelligence database
10
Role of Community Education
15

Evacuation Time Line modelling

Draw Critical time line include time available, mobilisation, traffic breakdown allowance, evacuation confirmation, travel time, time available for Door knocking, delay to vehicles movement, time available for vehicle movement

25
Discussion
15
Recommendation
10